Construction / Development of Market Complex at Naharkatia under special Central Assistance

Construction / Development of Market Complex

at Naharkatia under special Central Assistance

 

Total Project Cost                              :         Rs. 300.00 Lakhs

 

Financial Year                                   :         2013-2014

 

Date of Administrative Approval        :         30th October, 2013

 

Date of Work order                            :         6th June, 2014

 

Target time of Completion                  :         December, 2015

 

Revised target time of Completion     :         March, 2018

 

Project Detail                                     :         Ground Floor- 1226.52 m²

                                                                    First Floor- 1492.92m²

                            

Implementing Agency                        :         Town & Country Planning,  Dibrugarh

 

Physical Progress up to June, 2018  :         87%

 

Financial Progress                             :        62%

 

Fund Received                                   :         Rs. 225.00 Lakhs

 

U/C submitted for                             :         Rs. 150.00 Lakhs