Infrastructure Projects under 10% Allocation of Central Pool Fund provided for North East Region

Infrastructure Projects under 10% Allocation of Central Pool Fund provided for North East Region

CONSTRUCTION  OF  COMMERCIAL  MARKET AT  CHABUA  TOWN  UNDER  10%  POOL  FUND

Financial Year                                             :- 2013-14

Total Project cost                                         :- Rs. 814.91 Lakhs

Date of technical approval                           :- 17-05-2014.

Date of approval (GOI)                                 :- 16-12-2013.

Date of administrative approval                   :- 03-03-2014.

Date of work order                                       :- 01-07-2014.

Target time of completion                            :-  Feb, 2016.

Revised date of completion                          :- Dec, 2018

Implementing agency                                  :- Chabua Town Committee

Physical Progress up to June, 2018            : 39.62 %

 

Financial Progress                                      : 26.99 %

 

Fund Received                                            : Rs. 220.02 Lakhs

 

U/C submitted                                           : Rs. 220.02 Lakhs