  1. Construction of Town Hall at Dibrugarh Under NLCPR

Total Project Cost                                         :-  Rs 1408.17 Lakhs.

Financial Year                                              :- 2014-2015  

Date of administrative approval                   :- 11-11-2014.

Date of work order                                       :- 05-01-2016.

Targeted time of completion                         :- November, 2016.

Revised target of completion                        :- December, 2019.

Project Detail                                               :- Ground Floor 2102.00 Sq.m

                                                                   Mezz Floor  1814.00 Sq.m   

                                                                   First Floor 2177.00 Sq.m     

                                                                   Second Floor 1910.00 Sq.m

                                                                   Third  Floor 1326.00 Sq.m

Implementing Agency                                  :- Dibrugarh Municipal Board

Physical Progress up to June, 2018            : 33.25%

 

Financial Progress                                      : 25%

 

Fund Received                                            : Rs. 211.22 Lakhs

 

U/C submitted                                           : Rs.211.22 Lakhs